Force Dry

Force Drying Cemfloor Liquid Screed

If you have underfloor heating (UFH), this can help to speed up the drying process. The UFH can be switched on after 7 days at the minimum temperature, then gradually increased by around 5°C per day. This controlled commissioning process can reduce overall drying times by up to half.

For Cemfloor screed, typical drying times are:

  • Up to 50mm thickness: around 21 days
  • Above 50mm up to 75mm: around 28 days

Our team will be happy to discuss the UFH commissioning process with you in more detail when attending site to complete the screed.